Weekly Status Report
Mars Health Group
Project status
Financials
No purchase order has been raised against this project, so the PO budget and billed-to-date figures are zero. Contract value £138,610.80.
This week at a glance
Risks
| Ref | Subject | Latest update | Owner and due |
|---|---|---|---|
| 052180Raised 29/09/2026New | Historic appointment extract data quality | 29/09: Profile the extract in discovery, agree a per practice cleansing rule, and migrate 24 months rather than the full history. | Robert SindallDue 03/11/2026 |
| 052181Raised 29/09/2026New | Rota supplier interface rate limits | 29/09: Agree the cap in writing in discovery, and schedule the bulk read overnight inside a single batch window. | Robert SindallDue 18/11/2026 |
| 052182Raised 29/09/2026New | Clinical sign off competes with winter pressures | 29/09: Book the sign off slots in discovery and hold them, with a named deputy clinical lead as a fallback. | Robert SindallDue 28/12/2026 |
| 052183Raised 29/09/2026New | Historic care plan notes are unstructured | 29/09: Report on structured fields only, and leave the free text as a document the clinician reads rather than a figure the report sums. | Robert SindallDue 08/12/2026 |
One further open risk on this project is marked internal and is excluded from this client-facing report.
Actions
| Ref | Subject | Latest update | Owner and due |
|---|---|---|---|
| 052185Raised 29/09/2026New | Confirm the interface owner for each source system | 29/09: Ruth to confirm the three named interface owners following the weekly status meeting. | Robert SindallDue 20/10/2026 |
| 052186Raised 29/09/2026New | Book the design playback before the December freeze | 29/09: Playback confirmed for 12/10 with all three practice managers. | Robert SindallDue 29/10/2026 |
| 052187Raised 29/09/2026New | Agree the reconciliation tolerance with finance | 29/09: Tolerance agreed at one pound per site; awaiting written confirmation from finance. | Robert SindallDue 13/11/2026 |
Issues
| Ref | Subject | Latest update | Owner and due |
|---|---|---|---|
| 052188Raised 29/09/2026 | Rota extract arrived without the practice identifier | 22/09: Re-extracted with the practice identifier included and a checksum per file. Closed same week. | Robert SindallClosed 22/09/2026 |
| 052189Raised 29/09/2026 | Test data cannot leave the clinical system | 29/09: Generate synthetic patients that preserve the shape of the data without any real patient in it. | Robert SindallDue 13/10/2026 |
Decision
Delivered this period
No work items reached a delivered state in this period.
Blocked work items
No work items are blocked.
Notes
States the report has to handle
Four dimensions plus a derived overall. The org's stored values are OnTrack, Caution and Impact.
Shown when a purchase order exists. The percentage is derived, never typed.
11.3% of the PO budget billed to date · remaining £88,656.20
Populated form. Rows appear only when a work item reaches a delivered state inside the week.
| Ref | Work item | State |
|---|---|---|
| WI-167880 | Report performance and access review | Implemented |
| WI-167887 | Automation monitoring and error handling | Deployed |
Populated form, with the reason and the age of the block.
| Ref | Work item | Blocked |
|---|---|---|
| WI-167902 | Rota incremental read | 9 days |
Nothing recorded. The report still has to be a complete document, not a fragment.
No RAID items or notes were recorded for this week.